dc.identifier.citationBetita, L. D. (2002). A study to improve efficient islanding operation of 72 MW diesel engine power generating system of Panay Power Corporation (Unpublished Master's special paper). Central Philippine University, Jaro, Iloilo City.en_US
dc.identifier.urihttps://hdl.handle.net/20.500.12852/500
dc.descriptionAbstract onlyen_US
dc.description.abstractAt present, the 72 MW Panay Power Corporation operation department as well as the efficiency and result officer are very much aware of the situation that the ratio of fuel consumed by the system and the power generated is below its expectation. The performance of the generating units is focused and reflected on the fuel rate calculation on a day to day basis. The company is presently generating an average value of 1100 MWH a day and it is gradually increasing as months and years pass by. The total fuel consumed per day is more or less 25,000 liters. 99% of the total fuel used is Bunker C fuel. Only 1% or less is Diesel fuel depending on how efficient the generating unit operates, the fuel quality, range and variability of the load caused by external end users. However, fuel quality, engine trouble, power interruption, power factor adjustments and any other abnormalities encountered and took place during the operation will not be included in the discussion anymore. It will be explained further in the scope and limitation. The main concern of the company is concentrated on how to improve fuel rate or power plant efficiency thru operation side or operator’s point of view. This is what the study is all about. It includes reduction of fuel consumption while maintaining its generating power output. The first step is to identify and pinpoint the factors that affect power plant efficiency at normal islanding operation. Data pertaining to these factors will be properly analyzed and interpreted. Understanding these factors will give us a better perspective and idea on how to formulate, create and modify new operating strategy in order to improve efficient operation. It will also help, guide and give the operator the greater strategy to utilize and handle power plant equipment to optimum performance without compromising the durability of the unit and reliability of the system.en_US
dc.format.extentvii, 52 leavesen_US
dc.language.isoenen_US
dc.subject.ddcGSL Theses 620.0072 B465en_US
dc.subject.lcshDiesel motoren_US
dc.subject.lcshElectric power-plantsen_US
dc.subject.lcshPower resourcesen_US
dc.subject.lcshElectric utilitiesen_US
dc.subject.lcshElectric power productionen_US
dc.titleA study to improve efficient islanding operation of 72 MW diesel engine power generating system of Panay Power Corporationen_US
dc.typeSpecial paperen_US
dc.description.bibliographicalreferencesIncludes bibliographical referencesen_US
dc.contributor.chairDavid, Fely P.
dc.contributor.committeememberRio, Walden S.
dc.contributor.departmentSchool of Graduate Studiesen_US
dc.description.degreeMaster of Engineeringen_US
local.subjectPanay Power Corporation (PPC)en_US